Forum Discussion
Caracole
Feb 28, 2023Copper Contributor
Deadline print issue
Hello, I have a problem on my project when I try to print my schedule, the deadline takes priority over the link. An example on the following screenshot: On the first screenshot no prob...
- Feb 28, 2023
Caracole,
Your notes indeed indicate there is an issue with the file so this is what I suggest. Save your file as XML. Then re-open the XML file in Project. Let us know if that helps.
John
John-project
Feb 28, 2023Silver Contributor
Caracole,
Your notes indeed indicate there is an issue with the file so this is what I suggest. Save your file as XML. Then re-open the XML file in Project. Let us know if that helps.
John
Caracole
Feb 28, 2023Copper Contributor
Hello John-project,
Thank you for your answer.
The manipulation worked. Even if I lose all my formatting, I no longer have the bug.
So it is probably a parameter or setting of the file. For my knowledge I would like to know which one.
Caracole
- John-projectMar 01, 2023Silver ContributorCaracole,
You're welcome and thanks for the feedback.
File corruption can occur for many reasons but rarely is it due to a parameter or setting of the file. In most cases it is the result of the user doing some action that "confuses" the application. Without a good operational trail of what you did with the file prior to the issue, it is extremely difficult to nail down a specific cause. Sorry.
John