Forum Discussion
sirsleep29
Jul 10, 2023Brass Contributor
Date Range Filter
I am trying to use the date range filter in ms project and I put in my dates for let's say a 1 month timeframe but some of the tasks that come back when I run the filter are showing to be outside of ...
- Jul 11, 2023sirsleep29,
The task in your screen shot has a finish date that is "greater than or equal to" today's date. And it's start date is "less than or equal to" 8/11/23. So yup, it's in the date range.
I have always felt the structure of the Date Range filter is confusing, but, it does do what it says.
John
ismet_kocaman
Jul 11, 2023Brass Contributor
Hi Aaron,
I would search the internet for the subject. There are plenty of articles on the date range filters and lookahead filters on the internet such as the one below:
https://www.plannersplace.com/blog/how-to-create-a-rolling-date-lookahead-filter-in-microsoft-project
I hope this helps.
Ismet
PS. Prompt messages in the Date Range filter are confusing.
sirsleep29
Jul 12, 2023Brass Contributor
Thank you for your help Isaac
- ismet_kocamanJul 12, 2023Brass ContributorYou're welcome.