Forum Discussion

sirsleep29's avatar
sirsleep29
Brass Contributor
Jul 10, 2023
Solved

Date Range Filter

I am trying to use the date range filter in ms project and I put in my dates for let's say a 1 month timeframe but some of the tasks that come back when I run the filter are showing to be outside of ...
  • John-project's avatar
    John-project
    Jul 11, 2023
    sirsleep29,
    The task in your screen shot has a finish date that is "greater than or equal to" today's date. And it's start date is "less than or equal to" 8/11/23. So yup, it's in the date range.

    I have always felt the structure of the Date Range filter is confusing, but, it does do what it says.

    John