Forum Discussion
sirsleep29
Jul 10, 2023Brass Contributor
Date Range Filter
I am trying to use the date range filter in ms project and I put in my dates for let's say a 1 month timeframe but some of the tasks that come back when I run the filter are showing to be outside of ...
- Jul 11, 2023sirsleep29,
The task in your screen shot has a finish date that is "greater than or equal to" today's date. And it's start date is "less than or equal to" 8/11/23. So yup, it's in the date range.
I have always felt the structure of the Date Range filter is confusing, but, it does do what it says.
John
John-project
Jul 11, 2023Silver Contributor
sirsleep29,
You're welcome and thanks for the feedback. I've worked with Project since 1997 or thereabouts, so a couple of years anyway.
John
You're welcome and thanks for the feedback. I've worked with Project since 1997 or thereabouts, so a couple of years anyway.
John
sirsleep29
Jul 11, 2023Brass Contributor
John...lol....I had a 20 yr layoff from having to use Project so it is a learning curve for me....been back in it for about 4 months. I have done filters recently but never a date filter. Would you happen to have a good link to a place that would teach me how to create a date filter. I want to do a lookahead 6 month and 1 yr calendar. Thank You, Aaron
- ismet_kocamanJul 12, 2023Brass ContributorYou're welcome.
- sirsleep29Jul 12, 2023Brass ContributorThank you for your help Isaac
- ismet_kocamanJul 11, 2023Brass Contributor
Hi Aaron,
I would search the internet for the subject. There are plenty of articles on the date range filters and lookahead filters on the internet such as the one below:
https://www.plannersplace.com/blog/how-to-create-a-rolling-date-lookahead-filter-in-microsoft-project
I hope this helps.
IsmetPS. Prompt messages in the Date Range filter are confusing.
- John-projectJul 11, 2023Silver ContributorAaron,
Date filters aren't that difficult but they can be tricky. I contacted a colleague who does a lot of training on Project custom field formulas. I asked if he would jump into this thread and help out. I'll check back later to see if you get the help you need.
John