Forum Discussion
Data access after Project Online (PWA) retirement
As the retirement of Project Online (PWA) approaches, some questions have come up regarding what will happen to the data and related content.
I’d like to ask if anyone has information or guidance on the following points:
- What happens to the data currently stored in Project Online after the retirement date?
- Will this data still be available for viewing, export, or migration after that date? If so, for how long?
- Regarding the SharePoint sites linked to PWA, will they remain available? Will it still be possible to access or modify their content?
- Does Microsoft plan to publish official guidance on this transition?
Any references or practical experiences on this topic would be greatly appreciated.
16 Replies
- DaveMendlenCopper Contributor
The safe planning assumption is that access ends on the date, because Microsoft
hasn't committed to a grace period — and an archive you build in October is worth
nothing if the service is already gone.
Two things worth separating, because they get conflated and it matters:
**A reporting export is not a schedule.** The OData reporting feed
(`https://<tenant>.sharepoint.com/sites/pwa/_api/ProjectData/`) will give you
tasks, assignments and timephased rows, and it's the fastest way to bulk-extract
everything. But it's the reporting schema, not the scheduling model. It does not
preserve the network logic, constraints, calendars or baselines in any form a
scheduler can re-open. It's an excellent audit record and a useless archive if
you ever need to *reschedule* one of these plans.
**So export twice, in different formats, for different purposes:**
1. **Native .mpp per project**, from the Project desktop client. Highest fidelity
— this is the only artefact that preserves the actual schedule model.
2. **MSPDI XML per project** (Save As → XML). More portable and readable in ten
years than a binary format, and not tied to any one vendor. Be aware it does
not capture timephased Work and Cost values, so it isn't a complete
substitute for #1.
3. **OData pull** for the portfolio-level reporting record.
4. A PDF of each Gantt, if anyone will ever need to read these without software.
**Then verify before the date, not after.** Take three or four representative
plans — ideally ones with deleted rows, custom fields and real predecessor
networks — re-open the exports cold, and check that predecessors, constraints and
baselines actually survived. Finding out an archive is lossy while the source
system is still running is a recoverable problem. Finding out on 1 October is not.
Worth noting for anyone planning to land in Planner: Planner Premium has no MPP
export, so whatever you take out now is what you'll have. Plan the exit format
before the migration, not after it.
Disclosure: I'm an ex-Microsoft VP and I run projectkiller.app - a Mac based version of Project. - PablitoCopper Contributor
I have a question because i think it is not clear. What will happen with custom list? We have several lists created on PWA site that are not related with PWA info that we use for other business processes. Will that lists be unavailable as well?
- Leandro Cesar de Melhado e LimaBrass Contributor
Hi Pablito,
That's a great and very practical question, and unfortunately the answer is not what most people want to hear.
Based on the information I have gathered from multiple direct interactions with Microsoft (support cases, partner community meetings, and official replies on Microsoft Learn), the entire PWA site collection will become unavailable after September 30, 2026. This means that any content hosted on that site collection, whether it is related to Project Online or not, will no longer be accessible.
So to answer your question directly: yes, your custom lists created on the PWA site will also become unavailable, even though they are not related to PWA functionality and are used for other business processes.
The key point here is that Microsoft is decommissioning the PWA site collection as a whole. It does not matter whether the content on that site is project data, a custom list, a document library, or anything else. If it lives on the PWA site (or on a subsite created under the PWA site collection), it will be gone after retirement.
What you should do before September 30, 2026:
- Identify all custom lists and non-PWA content stored on your PWA site collection.
- Migrate those lists to a separate, standalone SharePoint site that is not tied to the PWA instance. You can use SharePoint native tools, Power Automate flows, or third-party migration tools to move the data.
- Update any links, integrations, or automations that reference those lists to point to the new location.
- Do not wait until the last moment. The retirement is a hard stop with no grace period and no read-only window guaranteed by Microsoft.
I've asked Microsoft this same question multiple times through different channels, and the answer has been consistent: everything under the PWA site collection goes away. Plan accordingly.
Hope this helps! If you have follow-up questions, feel free to reply here.
- Shardul PasareCopper Contributor
Hello Leandro Cesar de Melhado e Lima,
We are having below scenario in our environment and we are not sure about impact as well
Our PWA site collection is seperate site collection and I believe that as per Microsoft this site collection will not be accessible after retirement. But our projects sites are getting created as subsite under other site collection which has classic team site template. So wanted to check if there is any impact on these project sites of this retirement.
Thanks in advance
- Leandro Cesar de Melhado e LimaBrass Contributor
Hi Shardul,
Great question, and this is actually one of the most important distinctions in this entire retirement topic.
Based on the information I’ve gathered from Microsoft (including official replies and partner-level discussions), the impact depends primarily on where the SharePoint site is hosted, not just how it was created.
In your scenario:
- Your PWA site collection → will become unavailable after retirement
- Your project sites created as subsites under a separate (non-PWA) site collection → this is a different case
If your project sites are truly hosted under a separate SharePoint site collection (not tied to the PWA site collection), then there is a strong indication that they are not directly impacted by the PWA retirement itself.
However, there is an important nuance:
Factual (confirmed based on Microsoft guidance):
- SharePoint sites that are linked to Project Online and part of the PWA site collection will become unavailable after retirement
Hypothesis (to validate in your environment):
- If your project sites are:
- Hosted under a completely independent SharePoint site collection
- Not structurally dependent on the PWA site collection
Then they may continue to exist after retirement
Risk to consider (very important):
Even if the site physically remains available:- Any integration with Project Online (links, workflows, provisioning logic, metadata sync, navigation) will break
- Some project-specific features may stop working or become orphaned
- There is no explicit official Microsoft statement confirming long-term support for this hybrid scenario
So while the site itself may survive, its functional context as a “project site” may not.
Recommendation:
To reduce risk, I strongly suggest you:
- Validate if those sites are truly independent at the site collection level
- Identify any dependency on Project Online services (metadata, navigation, workflows, automation)
- Plan to treat them as standalone SharePoint sites going forward
- If they are business-critical, consider validating this behavior with Microsoft support for your tenant
In short:
- PWA site collection → definitely goes away
- External SharePoint site collections → likely remain, but with functional limitations and no guarantees
Hope this helps clarify your scenario.
- humphrieskTin Contributor
This thread is a little old, but I have a question related to this part:
2/ What about linked SharePoint sites?
SharePoint sites linked to Project Online (such as project workspaces) will also become unavailable after retirement.
You will not be able to access or modify these sites once Project Online is retired.All the resources I have seen here and elsewhere seem pretty clear about "project sites will not persist" or "you will not be able to access your project data, including SharePoint data." I still have one small faint hope.
We are planning a migration from PWA to another platform, but to minimize that migration I was planning to archive hundreds of old, closed, or completed projects first, in this fashion:
- export the Project Schedule as an MPP file
- upload it to the project Shared Documents library
- delete the project from the Project Center, while not deleting the SharePoint subsite
- set all user permissions for the SharePoint subsite to Read-Only
Important note: We not use the “PWA permissions mode”; we are only using the “SharePoint permissions mode”.
All the resources either don't mention the permissions mode or specifically say "your sites won't work because "the PWA permissions" won't be present". But we don't use PWA permissions mode -- we use SharePoint permissions mode. I simply cannot see what connection to PWA is remaining in those subsites once we archive the data and delete the project from the Project Center. That's my small hope.
Perhaps the answer will be "We (Microsoft) don't know what permissions mode you use, so we're going to delete everything anyway." That would be draconian, but at least it will be clear. But it dramatically increases the migration effort -- we have to migrate the active projects to a new platform AND migrate the "archived" SharePoint sites to a new SharePoint site.
Your thoughts, anyone?
- Leandro Cesar de Melhado e LimaBrass Contributor
Hi humphriesk,
I completely understand your reasoning, and honestly, your approach is technically sound from a SharePoint perspective. Under normal circumstances, if you detach a subsite from its business logic and rely only on SharePoint permissions, it should continue to exist independently.
However, based on everything I have confirmed directly with Microsoft (including multiple support cases, partner discussions, and official responses), the behavior here is not driven by permissions mode or logical dependencies. It is driven by the decommissioning of the PWA site collection itself.
This is the key point: once Project Online is retired, the entire PWA-backed site collection becomes inaccessible, not just the Project data layer.
Because of that:
- It does not matter if you use PWA permissions mode or SharePoint permissions mode
- It does not matter if the project is deleted from Project Center
- It does not matter if the subsite is read-only or “archived”
If the site (or subsite) is hosted under a PWA site collection, it is expected to become unavailable after retirement.
Most guidance, including official responses, consistently points to a hard cutoff where both Project data and associated SharePoint content become inaccessible after September 30, 2026.
So unfortunately, the “small faint hope” scenario, where detached SharePoint subsites continue to exist independently, does not align with what Microsoft has been communicating so far.
Practical recommendation:
If those archived sites are important, the safest path is:
- Migrate those SharePoint subsites to a separate, standard SharePoint site collection (outside PWA)
- Treat them as independent content repositories going forward
- Do not rely on permission mode or project deletion as a preservation strategy
I agree this significantly increases the migration effort, especially for archived content, but at this point it’s the only approach that aligns with the current Microsoft guidance.
Hope this helps clarify the situation.
Leandro --
To add to the excellent answers already shared, I think you need to assume that all of your Project Online data will be GONE after Microsoft "pulls the plug" on this tool. So, in other words, begin your planning immediately to move your Project Online data to another application, such as to Project Server Subscription Edition. In addition, I believe you will find that Microsoft IS NOT offering any of us help in migrating to Project Server SE, nor are they publishing any kind of official guidance. Hope these additional thoughts help!
- Leandro Cesar de Melhado e LimaBrass Contributor
Thanks, Dale,
We’re aligning our plans to the same assumption: once Microsoft “pulls the plug,” PWA data will be gone. That said, it would be extremely helpful if Microsoft could offer a **read-only retention window** (even limited) after retirement, for example, continued read access to PWA data and linked SharePoint project sites, or at least to the OData or CSOM export endpoints.
A short, time-boxed grace period (6–12 months) would let customers validate migrations, access historical records for audits, and avoid migrating large volumes of history they only need for reference. Given the tight timeline, this would significantly reduce risk and effort across tenants.
If you see any movement or formal statement from Microsoft on a read-only or historical access window, please share.
Leandro --
There is nothing unreasonable about your request, but at this point, I cannot imagine that Microsoft will ever grant that. They appear to be in a big rush to abandon Project Online, as well as the Project Online community of users. For years, they have assumed the world will migrate to Project Online, which later became Planner Premium, which has not happened. So, if I were you, I would come up with a plan to move to a another PPM tool, such as Project Server SE, and then execute that migration as soon as possible. Hope this helps.
- RodFrommSteel Contributor
Unless Microsoft changes their stance, none of the data in your MSP Online tenant will be available after MSP Online is retired. We are making plans to move our OData (used for Power BI reporting) to the dataverse then migrate our MSP Online PWAs over to MS Project Server SE.
- Leandro Cesar de Melhado e LimaBrass Contributor
Thanks, Rod, same view here.
Until Microsoft publishes official guidance on data retention, we’re planning under the assumption that PWA data and the associated SharePoint project sites won’t be accessible after retirement. If you see any official statement on post-retirement access/retention, please share it.
- John-projectSilver Contributor
Leandro. . .
Take a look at the following thread in this forum. Hopefully it will answer at least some of your questions.
What MS Project Online Retiring Means | Microsoft Community Hub
John
- Leandro Cesar de Melhado e LimaBrass Contributor
Thanks, John,
I watched the thread you pointed to (great overview).
We also published a video covering the retirement topic (for context: https://youtu.be/R4gtv-RgR9g - the video is in Portuguese, but it can be auto-captioned in English).
My question here is narrower and more practical: what exactly happens to the data after the Project Online (PWA) retirement date?- Will the data currently in Project Online remain accessible (even read-only) after retirement, and for how long?
- Will tenants still be able to view/export/migrate their data after the date? If yes, what’s the time window and supported mechanisms (e.g., OData/reporting DB, CSOM/REST, etc.)?
- Regarding the SharePoint project sites linked to PWA, will they remain available (and editable) as standard SharePoint sites? For how long and under what constraints?
- Is there an official Microsoft guidance or policy page that states data accessibility/retention timelines to help customers plan migration and compliance?
If you (or someone from Microsoft) can share the official documentation or a definitive statement on post-retirement data access and retention, that would be extremely helpful for customers planning migrations and audits. Thanks in advance!
- RodFrommSteel Contributor
I probably should have been clearer but in the conversations, I've had with Microsoft they stated the MSPO data will not be accessible after MSPO is retired. Here is the official announcement, which you've probably seen Microsoft Project Online is retiring: What you need to know | Microsoft Community Hub
- Will the data currently in Project Online remain accessible (even read-only) after retirement, and for how long?