Custom View with Subset of Tasks
Hi, How can a view be created which shows the subset of tasks, based on a few criteria ? One straight forward way is to put filters in Gantt chart view and show only the tasks which pass the ...
- May 05, 2022NKumar2010 --
First, create three custom filters: one for Sales tasks, one for Marketing tasks, and one for IT tasks. Then create three new custom views, each of which uses the Gantt Chart screen, and each of which uses one of the three custom filters you created. Hope this helps.
May 05, 2022
NKumar2010 --
First, create three custom filters: one for Sales tasks, one for Marketing tasks, and one for IT tasks. Then create three new custom views, each of which uses the Gantt Chart screen, and each of which uses one of the three custom filters you created. Hope this helps.
First, create three custom filters: one for Sales tasks, one for Marketing tasks, and one for IT tasks. Then create three new custom views, each of which uses the Gantt Chart screen, and each of which uses one of the three custom filters you created. Hope this helps.