Custom text field value in the report graph

Hi,

I am using one of the custom text4 field to convert the number to percentage. My question is how to get these values in the Graph report, I  can take this values in the table but not able to find custom field list.

I noticed the custom field list is different when I select the graph than the table. I attached both picture

to compare.

 

 

TABLE CUSTOM FILELD LIST:

 

 

GRAPH CUSTOM FILED LIST:

 

GRAPH TO ADD TEXT4 VALUE

1 Reply

  • John-project's avatar
    John-project
    Silver Contributor
    jhonex1,
    You don't see custom fields in the pick list for a graph because a graph is time based and custom fields are static (non-time based). Generally, whatever data you can see in the timescaled data (right side) of either Usage view, can be added to a custom graph.
    John