Custom Task Level Field Using Formula not Available in Timesheet View
I want to show a project-level field in PWA timesheets so I created a custom task-level field that uses a formula to point to the project level field. This formula works as I can see the field correctly filled out in the project plan when i add the column to the Task Usage View.
My issue is that the field is not in the Available fields to show when I try to edit the My Timesheet or My Work views. I did ensure that the tasks setting for "Calculation for Assignment Rows" was set to "Roll down, unless manually specified".
Thanks,
Mark
2 Replies
- Stoney35 --
If memory serves me correctly, Project Online and Project Server will not allow the app admin to add custom fields with formulas to either the Timesheet page or the Tasks page in PWA. Hope this helps.- Stoney35Copper ContributorOK, so nothing I'm doing incorrectly. Just not possible.