Forum Discussion
Custom Task Field Value Not Show In Report
Hi John-project ,
Below is the Gantt Chart View of the file which include customize "Plan %":
The "Plan %" formula I use is as per below:
And under report, I would like to show the summary value of "Plan %" for "Elite Comfort", which currently is not showing any value.
I think you will need to download the file in order to view it because currently google chrome dont have an extension that can open ms project file.
Hope you able to help me on this.
Thanks & Regards,
Tony
Your screen shots are helpful and unfortunately do not provide all the information I need to help you. For example, I don't know what your field list settings are for the Project Overview report. The "Late tasks" table on the report shows a single line of a task with the Elite Comfort resource but that doesn't match up with any task line shown in the screen shot of your Gantt Chart. I do see you have selected the Text1 field but there is no information about filter, group, outline level, or sort, which are all part of the field list selections.
I cannot download your file because it is a view file only, not the actual Project file (i.e. .MPP). However you can send the file to me at the address below. I will ask some questions.
John
jmacprojataticlouddotdotcom
(remove obvious redundancies)
- Tony_CheahJul 28, 2021Copper Contributor
Hi John,
The "Late tasks" table on the report shows a single line of a task with the Elite Comfort resource only because I'm trying to show a summary view of Elite Comfort current work status.
I had send the file to your email, but not sure if I send to the correct email.
Let me know if still havent received.
I had change the setting of the file in my share drive to be able to edit by anyone with a link. So maybe you can try the link again also if the file was not send to your email.
Thanks & regards,
Tony
- John-projectJul 28, 2021Silver Contributor
Sorry, I did not get an e-mail from you and I still cannot download from the link you provided. However, I think I may have figured out what's wrong. Please show a screen shot of the Field List for the Project Overview report.
I'm guessing you have selected fields for "Resources" instead of fields for "Tasks". If so, then that's why you won't see any values for the Text1 field. The Task Text1 field is NOT the same field as the Resource Text1 field. Please refer to the following Wiki article:
If that does not directly answer your question, then please try sending me the file again. Read the encoded e-mail address I provided carefully.
John
- Tony_CheahJul 28, 2021Copper Contributor
Hi, below is the screenshot of Field List, I selected Resources Names for Tasks list. Not sure if this is the reason the value is not showing.
By the way I had try to email you again, I think I manage to decode your email this time.
Thanks & regards,
Tony