Forum Discussion
ralphobarly
Oct 12, 2022Copper Contributor
Custom Filter for Custom Field
Hey All, I'm attempting to create a custom filter that will only show the tasks of which the custom field/column value is a specific value (in this case A, B, C, D ). Custom filtering in the tas...
ralphobarly
Oct 12, 2022Copper Contributor
Thanks for the reply. I've just tried that, and it also doesn't work. When I use the autofilter to sort equals A, that works, however. Not sure if that helps?
PlannersPlace
Oct 12, 2022Brass Contributor
- ralphobarlyOct 12, 2022Copper Contributor
PlannersPlace Hmm. I have some screenshots of me doing an identical filter and no results. I'm not sure how to upload an image to demonstrate this. When I click on insert/edit image, I'm given a few blank fields for text entry, and that's it. Thanks again
- PlannersPlaceOct 12, 2022Brass ContributorFor screenshot, use a snipping tool & save the image.
check that you have just "A", "B" as values in custom field and not "A ", "B "
note the spaces- ralphobarlyOct 12, 2022Copper Contributor
PlannersPlaceAh yes. Apparently I do not have permission to upload images to this forum. I'm not sure what that takes I've checked for spaces, no dice. I can see how this is difficult to help troubleshoot sans images.