Custom fields for subprojects
Hi, I am using Microsoft® Project® Online Desktop Client MSO (Version 2309 Build 16.0.16827.20166) 64-bit. I have one master file which contains bunch of subprojects (one subproject for one build...
Oct 24, 2023
OndraValek --
No, it is NOT possible to create custom Project fields using the Microsoft Project desktop application. That particular feature is only available if you are using Project Online, which is a true enterprise application. Sorry, but hope this helps.
No, it is NOT possible to create custom Project fields using the Microsoft Project desktop application. That particular feature is only available if you are using Project Online, which is a true enterprise application. Sorry, but hope this helps.