Forum Discussion
RaulVV
May 30, 2023Copper Contributor
custom field in timesheet
Hi, I create a new field of enterprise. I add in the timesheet view the new field and also add the column in a planning and fill in some data of the field in some task. Once the schedule is publis...
RodFromm
Jun 01, 2023Iron Contributor
Can you provide some clarity as the suggestions will vary drastically.
~ I take it you have created a new custom task field?
~ You added the task field to a Timesheet view?
~ The new task field does not show up in your timesheet using the modified view?
Is the task not appearing in the timesheet, the new column, or neither?
If the
~ I take it you have created a new custom task field?
~ You added the task field to a Timesheet view?
~ The new task field does not show up in your timesheet using the modified view?
Is the task not appearing in the timesheet, the new column, or neither?
If the
RaulVV
Jun 02, 2023Copper Contributor
I have created a custom company field with "Entity and Type" as Task and Text.
I have added the custom field to a Timesheet view.
In the Timesheet the column of the field appears correctly.
I make a new schedule and add the custom field column. It appears as a company custom field. So far so good.
If I give a value to the field in the schedule and then publish, the added value does not appear in the custom field column in the Timesheet.
If I give a value to the custom field in the Timesheet, I send it for approval, it is approved but when I open the planning the field appears empty, with no value.
I have also tried the solution proposed by Dale_HowardMVP and it doesn't work either.
I have added the custom field to a Timesheet view.
In the Timesheet the column of the field appears correctly.
I make a new schedule and add the custom field column. It appears as a company custom field. So far so good.
If I give a value to the field in the schedule and then publish, the added value does not appear in the custom field column in the Timesheet.
If I give a value to the custom field in the Timesheet, I send it for approval, it is approved but when I open the planning the field appears empty, with no value.
I have also tried the solution proposed by Dale_HowardMVP and it doesn't work either.