Forum Discussion
Custom Columns in Project Professional won't update in project online or task view
Paul, the information you shared previously worked very well to get the custom columns to talk between project professional and the web app version in the project center. It was easier to set them up than it was to update all the schedules 🙂
I still seem to be hung up getting things flowing for an assignee to see their assignments in the "Tasks" screen of the web app. For a bit more detail, we have multiple projects feeding into the master. Our hope is that a resource can sign onto the web app and see all their tasks as they would in a task view with the master opening. At the moment, don't seem to be getting but a handful of the tasks out of 1 schedule then none of the data in the now enterprise custom columns.
If you need more detail, let me know.
Thank you Paul and community in advance for all your help!
Had to block out some detail to keep privacy up.
Mike Sullins
Hi Mike Sullins ,
Some things to check:
- If some tasks are appearing and others not on the Tasks page - is the difference between a task that is appearing and a task that isn't? Any filters on the Task page view?
- For the Task level custom field, if you want this on the Task page - have you set that field "Calculation for Assignment Rows" to roll down on the Enterprise Custom Field setting in PWA Setting? If this is currently not set to roll down to the assignment, update the field settings then open the project and republish the project plan and try again.
Paul
- Mike SullinsMar 25, 2020Copper Contributor
Paul, Seem to be making some good headway. I now get 4 of the 6 columns showing data on the task view under the "My assignment" enterprise view. I have confirmed all 6 custom columns are set up the same with the "roll down setting, unless manual" which is my only option besides no. I republished the project and still don't have data showing in the last 2 columns.
Is there a limit of 4 custom columns, or a setting buried in the PWA?
Other thoughts?
Thanks in advance for all the help!
- Paul_MatherMar 26, 2020MVP
Hello Mike Sullins ,
Great to hear that you're making good progress. Regarding the two fields not showing the values, did you happen to have Project Professional already open and connected to the PWA instance whilst making these changes to the Enterprise Custom Fields? If so, close down Project Professional, launch it again, open the project and publish it. Once that completes in the PWA queue, try the Tasks page again.
Paul
- Mike SullinsMar 27, 2020Copper Contributor
HelloPaul_Mather ,
Paul, that seemed to work, had apparently 2 issues, 1 as you described and a second one that was hard to pickup on. The last few columns when I inserted them, didn't insert the column that was highlighted apparently because I hit enter instead of purposely left clicking on the one to insert. Detection of this was difficult because I had a very similar named field for enterprise and non-enterprise, example "Fab (E)" is an enterprise and the system kept selecting (when I hit enter) Fab E with a line thru the "E" indicating it was not an enterprise field.
Once I resolved this issue which occurred randomly thru multiple projects, republished them, all works well EXCEPT.
Next question.
It seems even though the system seems to be working as designed, if my test user makes a change to one of the custom enterprise columns in the web app "Task" view (my assignments) it doesn't backflush even thought the test user clicks submit all changed tasks, the project manager approves the changes. The secondary is that the "Task" view remains as changed on its view and the project in the web app and project professional remain as they were, aka not showing the submitted and approved changes.
Again, Thanks in advance for you help and your patience.
Mike Sullins