Custom Column for Poject Tasks

User created a custom column in Project for the Web, but I don't see it in the Project Tasks Dataverse Table. It is a choice column.  How can I find out what table this column gets added to behind the scenes in Dataverse

 

 

1 Reply

  • Custom fields do not appear anywhere in the Dataverse with Project for the Web. Perhaps this feature will be added to the software in the future, but it is not available in the current version. Sorry, but hope this helps.