CSOM Project Online timesheet for resource per day
Do you allow future-dated time entry?
PWA Settings > Timesheet Settings and Defaults > Allow future time reporting
Hey Ian, Thanks for your reply. That settings has already been allowed. I'm just not sure if the issue that I was experiencing is coming from a configuration side or the CSOM code itself.
I was able to entered in time for the initial date, but when my application synchronize to put more actual hours on the next day, that doesn't work. However, I figured that if I delete the task from the schedule and re-synchronize the task back to the timesheet, that will work and set me the actual hour to multiple days.
Any other suggestions, I also have created a ticket to microsoft regarding this issue.
- Ian BrucknerJun 14, 2018Iron Contributor
That was my "easy" guess. To understand better, though, would you care to share your code?