Critical tasks on Gantt chart view on SharePoint project Site
Hello, We are on Project server 2019 on Premise system. The projects are published to the PWA and have connected a SharePoint site for the project. The SharePoint project Tasks page shows project...
Aug 29, 2024
Ana-S --
If you are using the SharePoint Tasks List feature in Project Web App, then no, there is no way to display a Gantt Chart or Critical Path. Sorry, but hope this helps.
If you are using the SharePoint Tasks List feature in Project Web App, then no, there is no way to display a Gantt Chart or Critical Path. Sorry, but hope this helps.
Ana-S
Aug 29, 2024Brass Contributor
There is a Gantt chart view for the Task list. Is there a way I could extend the view to show Critical Task?
- Aug 29, 2024Ana-S --
Well, now I am totally confused. Please share a screenshot of what you are looking at in PWA so that I can better answer your question. Thanks!- Ana-SAug 29, 2024Brass Contributor
- Aug 29, 2024Ana-S --
Well, I stand corrected! I never use the SharePoint Tasks List feature in Project Online, so I was totally unaware that you can apply a Gantt Chart view to the task list. Sorry about that! 😞
So, I want to the Project Site for one of my enterprise projects, displayed the Tasks page, and then displayed the Gantt Chart view. When I clicked the "Modify this view" item, I was hoping to see that the Critical column was avaialable for inclusion in this view. Alas, the Critical field IS NOT available. So, I think you are out of luck. Sorry about that!
Out of curiosity, what exactly are you trying to do with the Tasks page in the SharePoint site? If you could explain further, maybe there is another way to meet your needs. Please let us know and we will try to help you.