Forum Discussion
Ana-S
Aug 28, 2024Brass Contributor
Critical tasks on Gantt chart view on SharePoint project Site
Hello, We are on Project server 2019 on Premise system. The projects are published to the PWA and have connected a SharePoint site for the project. The SharePoint project Tasks page shows project...
Ana-S
Aug 29, 2024Brass Contributor
Thank you, Dale. The task list is on PWA Project SharePoint Site.
The Project schedule is synchronized to the SharePoint Task list on Project site. I don't see option in the task list to select/set Critical Task.
The Project schedule is synchronized to the SharePoint Task list on Project site. I don't see option in the task list to select/set Critical Task.
Aug 29, 2024
Ana-S --
If you are using the SharePoint Tasks List feature in Project Web App, then no, there is no way to display a Gantt Chart or Critical Path. Sorry, but hope this helps.
If you are using the SharePoint Tasks List feature in Project Web App, then no, there is no way to display a Gantt Chart or Critical Path. Sorry, but hope this helps.
- Ana-SAug 29, 2024Brass ContributorThere is a Gantt chart view for the Task list. Is there a way I could extend the view to show Critical Task?
- Aug 29, 2024Ana-S --
Well, now I am totally confused. Please share a screenshot of what you are looking at in PWA so that I can better answer your question. Thanks!- Ana-SAug 29, 2024Brass Contributor