Critical task row red
Good day every one. So, when i took over this schedule, some really important tasks (maybe 8-10) were manually colored blue and green. So i changed their color back to normal (black). Some of THESE ...
John_Frantzen
Jan 19, 2022Tin Contributor
In my experience, once someone goes in and manually edits the bar display, it will NEVER revert back to the intended/default (system controlled) format. I may be wrong, but that is my experience. Unfortunately, I am very busy and don't have time to do software testing. I ran into this issue 20-25 years ago... and learned a lesson. Maybe... delete the activity, add a new/replacement activity, re-link the network logic, etc. -- and THEN maybe it will respond as it should color-wise. That is why anyone who uses MSP for serious or professional purposes (CPM scheduling) should refrain from all of the tiddly-wink formatting nonsense. Keep it simple. Use Bar Styles if you must (to make things function... i.e., define a "critical bar" which for some reason MSP does NOT do straight out of the box) but other than that, let the system control the bar display.
John_Frantzen
Jan 19, 2022Tin Contributor
My apologies, you were referring to the TABLE display, not the bar display. I do not typically engage in a lot of one-off formatting, so I'm not sure how to address your issue. Maybe... create a new table and associate the table with the view.
- willard800Jan 19, 2022Tin Contributorthanks for responding, but Dale's comments help me resolve the issue. Regards!