Forum Discussion
willard800
Jan 19, 2022Tin Contributor
Critical task row red
Good day every one. So, when i took over this schedule, some really important tasks (maybe 8-10) were manually colored blue and green. So i changed their color back to normal (black). Some of THESE ...
willard800
Jan 19, 2022Tin Contributor
Thanks for responding, tried it, did not work
John-project
Jan 19, 2022Silver Contributor
Will,
Then I think Dale hit the nail on the head, those tasks are in fact, not on the critical path.
John
Then I think Dale hit the nail on the head, those tasks are in fact, not on the critical path.
John