Forum Discussion
Creating production schedule in Project
Yes you can create custom fields for color, size or any other attribute and you can even group on those fields. But custom fields are independent of Project's scheduling engine, custom fields are simply adjunct information.
Keep in mind that leveling only applies to resources, information in custom fields cannot be "leveled".
John
If so, then it simply means we can not schedule based on color/size/such attributes and if there are no other ways to achieve it in MS project, then I would infer MS project is not suitable for production scheduling. I was hopeful that this would be achieved, at east with some tricks etc.
- mkjainSep 22, 2024Brass Contributor
RodFromm ,
I tried to create a simpler example on the link below:
https://docs.google.com/spreadsheets/d/1mHOdtK6_3zPY89O6aBfbJ-QHhW2kus47/edit?usp=sharing&ouid=101171441246165589914&rtpof=true&sd=trueEach bold row item indicated as firstone, secondone is a summary task, which basically is a finished product, and M1, M2, M3 are the machines for three different process stages. There will be multiple machine suitable for a stage, and we will allocate the one while creating a schedule.
I will try to keep similar color product as closely scheduled as possible, if in all cases it may be not possible that's fine, similarly at another stage I will prefer to keep same size product near by scheduled.
I have seen "Siemens Opcenter" as an alternative for this purpose, you may find it on internet.
Opcenter Production Scheduling for Plastic Injection Molding - ATS Global
https://www.youtube.com/watch?v=nzPnpAsS4PA
APS vs ERP Scheduling: What APS Does that ERP Does Not (Opcenter Planning & Scheduling Webinar)
https://www.youtube.com/watch?v=ffcOSuskqEs
Basically we are able to schedule it well, challenge is current practicle does not care if all or most blue are nearby scheduled? so we need to do many set up changes if wish to follow, do you find some workaround? Please suggest.