Forum Discussion
Matthew Russell
Nov 18, 2022Copper Contributor
Create a list specific to a project
Hi Hoping someone can help / give me some options I would like a way to create a project details page (similar to issues / risks) which is specific to each project. This would then be added to the ...
Paul_Mather
Nov 18, 2022MVP
Hi Matthew Russell ,
A list on the Project site would be the best option then surface this on a PDP similar to below if you didn't want to develop a full web part / app part:
https://pwmather.wordpress.com/2015/05/12/projectonline-projectserver-2013-access-sharepoint-lists-on-pdps-javascript-jquery-office365/
Or you could create these as tasks in the schedule similar to below (not ideal but might be an option for you):
Paul
Matthew Russell
Nov 21, 2022Copper Contributor
Hi Paul
Thanks for the response.
Apologies, when I said SharePoint page in my original query I mean SharePoint list.
Ive made a list but it Im not sure how to make it project specific, i'll go over your article to see if that helps
I did think about your second option but i dont think it would be intuitive enough for the team so a list is definitely the better option
Thanks
Matt
Thanks for the response.
Apologies, when I said SharePoint page in my original query I mean SharePoint list.
Ive made a list but it Im not sure how to make it project specific, i'll go over your article to see if that helps
I did think about your second option but i dont think it would be intuitive enough for the team so a list is definitely the better option
Thanks
Matt
- Harshad_SarodeFeb 24, 2023Copper ContributorCreate a custom field with drop down options and add that on the PDP page
- Matthew RussellFeb 27, 2023Copper Contributor
Thanks for responding
Unfortunately this would not be an option as we have thousands of products.
The solution needs to be free text and separate to the schedule page. This is why I was hoping for something like the risks and issues page
Thanks
Matt