Cost resources are not settled
Hello, At first, I have a problem with MS Project 365 and at second I hope I used the right names for fields etc. I'm using the german version. When I assign a cost resource to a task and the ta...
John-project
May 18, 2023Silver Contributor
Peter_Wagner,
Interesting, I don't know of any reason why cost type resource would be "settled" any different when other types of resources are also assigned to a task. I believe it is a bug.
As an alternative, you might consider using a fixed cost on the task instead of a cost type resource when multiple resource types are assigned.
John
Interesting, I don't know of any reason why cost type resource would be "settled" any different when other types of resources are also assigned to a task. I believe it is a bug.
As an alternative, you might consider using a fixed cost on the task instead of a cost type resource when multiple resource types are assigned.
John