Forum Discussion
__Thomas__
Aug 30, 2023Copper Contributor
Cost of a Cost type resource in the Task usage view
Hello everyone, When putting in the 'Gantt chart view' a certain amount of money in the 'Cost column' of a task assigned to a 'Cost type resource', this cost is not reflected in any cost field (C...
John-project
Aug 30, 2023Silver Contributor
What version of Project are you using?
This is what I get for a task with both a work type resource and and a cost type resource assigned to a task. Both costs appear as expected in the Task Usage view. How are you assigning the costs?
John