Forum Discussion
khyron
Apr 20, 2020Brass Contributor
Cost and Schedule Health in PWA (and for PowerBI Template)
Hi there I have recently added the PowerBI app for PWA and was wondering how is Cost and Schedule Health calculated? There are no fields of that name in my PWA custom fiels list. All the indi...
- Apr 21, 2020
Hello khyron,
They are calculated in the Power BI file using a DAX expression which uses data from default fields in Project Online, see this post for details:
Paul
Paul_Mather
Apr 21, 2020MVP
Hello khyron,
They are calculated in the Power BI file using a DAX expression which uses data from default fields in Project Online, see this post for details:
Paul
- khyronApr 25, 2020Brass Contributor
Paul I'd shake your hand if I could.