Corrupted file/ changes not saved

Hello,   I need your help.  I saved mpp (I'm using Microsoft Project Standard 2016) under two different names. When opening the first one no changes are visible, when opening the second one it says...
  • John-project's avatar
    Oct 05, 2022

    ziolo2310 

    If you can open at least one of the files I suggest you save the file as XML. Then re-open the XML file in Project. That often clears corruption. It likely won't recover your edits but at least it will be a "clean" starting point.

     

    For the file that won't open, there are 3rd party utilities that claim to be able to recover corrupt Project files but I have no first hand experience so can't recommend any.

     

    Why did your files go bonkers? It's hard to tell. If you are working on the files over a network it could have been a server glitch. If the file is part of a linked structure (i.e. master/subprojects or resource pool/sharer), those structures are prone to corruption.

     

    John