Correlation ID in project for the web
Hi, Trying to assign a new calandar template to a project. The calandar template is created in the project app in power apps. Not posible to assign it and gets a Correlation ID is there a way...
kblarsen
Mar 01, 2024Copper Contributor
RodFromm Thanks for information.
Have tried that and can change the template, but in the project I cannot see any effekt in project plan.
The non-workdays set in teh template are still used as workdays
The sss task is plan in a non-working day periode.
/Kim
RodFromm
Mar 01, 2024Iron Contributor
kblarsen Compare the assigned project calendars, to the calendar assigned to the resources on your project? If they are different that could be the issue. Also remember when you assign a calendar to a project or resource it applies a copy of the calendar. If you later change the calendar you have to remove and reapply it for the changes to be applied (it's not dynamic).