Correlation ID in project for the web
kblarsen Can you provide a screenshot of what you are doing, because it is possible to create new calendar templates and assign them to projects and resources.
Here is an article with additional information Create and apply a work calendar in Project for the web - Project for the web | Microsoft Learn
- kblarsenFeb 26, 2024Copper Contributor
RodFromm Hi,
I am trying to do what you and the article are writting.
Have created a new template calendar as shown below:
When I try to select and use it in a project I get:
/PC, Kim
- RodFrommFeb 26, 2024Iron Contributor
kblarsen That error message is related to a bug, which I submitted to Microsoft. Currently if a project was created in Project Accelerator is opened from the Project Home page you have access to Calendar Setting that are not available in the Project Accelerator. This can be very confusing. They are working on fixing this issue so the Calendar options are the same whether you are in the Accelerator, or open the project from the Project Home page..
To assign a different calendar to a project, go to your Project Accelerator, open the project then go to the Summary form and assign the new Calendar template as shown below