Correct resource allocation counting for person with partial workload
Hi, if a resource (person) has an overall 75% workload, how can I get MS Project to calculate resource usage % from 75% workload and not from 100%? E.g., Resource max unit = 75%. But if some task i...
IP_EST
Jul 04, 2022Copper Contributor
John-project
Jul 04, 2022Silver Contributor
What you are looking at is the % allocation and that is simply 85%/75% = 113%. I believe what you want to see is the % overallocation which is the overallocated work divided by the available work. In your example that will be 16.8h / 126h = 13.3%.
Unfortunately that value is not an available metric in Project. And to get that value as timescaled data, Project data must be exported to Excel to calculate and display the value per time period.
If % overallocation is not what you are seeking, then please explain in more detail.
John