Correct resource allocation counting for person with partial workload
Where exactly are you seeing 113%? In this example, the resource Max Units is set at 75%. That resource is then assigned at 85% which of course produces an overallocation but the assignment units and the peak units are at 85%.
John
- John-projectJul 04, 2022Silver Contributor
What you are looking at is the % allocation and that is simply 85%/75% = 113%. I believe what you want to see is the % overallocation which is the overallocated work divided by the available work. In your example that will be 16.8h / 126h = 13.3%.
Unfortunately that value is not an available metric in Project. And to get that value as timescaled data, Project data must be exported to Excel to calculate and display the value per time period.
If % overallocation is not what you are seeking, then please explain in more detail.
John