Forum Discussion
Cooperation with Microsoft Project .
Hi Damian_Dbrowski ,
Could you confirm the requirements? Are you looking for co-authoring like you can with Word and Excel Online? Or are you looking for audit tracking, who modified the project file and when?
Paul
- Damian_DbrowskiJun 15, 2020Copper Contributor
it will be great, if i have two options 🙂
You know, when i used example Excel or Word work is really easy. I would like to follow work with my friends from team.
- who changed files,
- who add new task etc.
Damian
- Paul_MatherJun 15, 2020MVP
Hello Damian_Dbrowski ,
There used to be the log level manager in Project Server 2013 - I'm not sure if that is still available for Project Server 2019 https://pwmather.wordpress.com/2012/07/26/projectserver-ps2013-log-level-manager-sp2013-sharepoint-msproject-powershell/
Otherwise you can either build your own audit app or look for a 3rd party app such as Fluent Pro Audit Manager: https://fluentpro.com/audit-manager I've never used the Fluent Pro Audit Manager tool but from the site above it looks like it might give the auditing you are looking for.
Paul
- Damian_DbrowskiJun 15, 2020Copper Contributor
i am greatfull for help. I have yet a little questions for. Scenario is: when I'm working on a shared file and someone is making their changes. I would not like to overwrite his changes. Do you understand me ? 🙂