Constraint Types defaulting to Start No Earlier than
hi, when enterning new tasks in MS Project (Office365). The task defaults to "Start no Earlier than" and i would like it to stay as As soon as possible". The project is set that each new tas...
Aug 29, 2024
parlinsingh --
The SNET constraints are appearing automatically because of the Project Options setting that causes each new task to Start on the current date. Change this setting to Project Start and your problem will disappear. Hope this helps.