Connect MS Project to multiple MS Planner plans

Hi,

I am using a single MS Project file for overall management of multiple sub-projects.

Can I connect the MS Project file to Multiple MS Planner plans?

6 Replies

  • KenPb --

    First of all, to connect a Microsoft Project schedule to a Planner plan, you must be using Microsoft Project with Project Online, and the project must be an enterprise project that has been saved and published in Project Online. Assuming this is true in your situation, yes, you can connect a single project to multiple Planner plans. You do this by connecting a task to a Planner plan. The limit is one Planner plan per task. Make sense? Let us know. Thanks!
    • KenPb's avatar
      KenPb
      Copper Contributor

      Hi Dale_HowardMVP, Thank you very much for the quick response.  Very much appreciated.  The corporate license I currently have is for MS Project Professional so that explains why the Planner connectivity is not enabled.  I have requested the MS Project Online version so that we can utilize this powerful feature.

      A follow-up question.  I have created a number of MS Planner plans, once I have the Online version, when I create a task and assign it to a resource, and assocaite the task to a bucket in Planner, does the task automatically generate in the bucket?

      Have a good safe day.

      Best regards,

      Ken Pitre

      • Ken --

        No, the feature in Microsoft Project only creates a hyperlink from the task in the project to the Planner plan. There is no interaction between Microsoft Project and Planner. I know the lack of functionality with this feature disappoints people, but it is what is is. Hope this helps.