Configuring Primary Cost Constraints to Develop Portfolio Analysis
I'm a new user to MS Project but have used other PMP tools. I'm trying to get initial configuration of the tool up for my new company, but have struggled with developing a portfolio analyses due to n...
- Feb 14, 2024Hi,
If you wish to use a custom field the field must be an enterprise custom field on the project level and of type cost
malshayeb
Feb 14, 2024Brass Contributor
Hi,
If you wish to use a custom field the field must be an enterprise custom field on the project level and of type cost
If you wish to use a custom field the field must be an enterprise custom field on the project level and of type cost
KyleKWX
Feb 14, 2024Copper Contributor
malshayeb Thank you! I was tying the custom field to the task and resource entities, not project. One final follow up question. I've applied that custom field into a few test projects to see what I get and although the custom cost field has data applied, I'm not seeing that project cost when running the portfolio analysis.
- KyleKWXFeb 15, 2024Copper ContributorUgh... realized you just key the cost detail directly into the portfolio analysis. Really thought the project task and resource allotment at the project level would drive this.
- malshayebFeb 19, 2024Brass Contributoryou can, but you need to have the proper setup, i think this guide would be helpful https://learn.microsoft.com/en-us/projectonline/portfolio-analysis-overview