I don't quite understand your statement, "I do not want graphical indicators in my subproject line". What exactly do you mean by "subproject line"? Are you referring to the summary line insertion points in the master like I show in my screen shot? So where exactly do you, and do you not, want the graphical indicators to appear?
Where you apply graphical indicators is up to the user. It just becomes a little more challenging when working with a master file with inserted subprojects.
Before you get to comfortable with master/subproject structures in Project let me inform you of some rules. Never rename, move, overwrite, or save off to another location any of the files in the structure. Dynamic masters (master with inserted subprojects) in Project are prone to corruption. Violating the above will practically guarantee the structure will get corrupted. Also, it is best to keep all files in a single folder on a local drive and not operate over a network.