Forum Discussion
Conditional Formatting in Custom Field not printing
I think the issue you are dealing with is that the master does not actually contain subproject tasks, rather, the master only contains pointers to each subproject. You can readily see this by looking at the ID field. For those tasks that are in the master (i.e. subproject summary line insertion points) you will see one set of IDs, consecutive but spaced apart by subproject tasks. Within each subproject you will see the IDs in their normal consecutive sequence, assuming you have not applied a sort or filter.
The limited screen shot you show is a task with and ID of 1. I don't know if that is the summary line insertion point for the first subproject or if it is the first task of a subproject.
Can you get what you want? Yes, but it will take some steps to do so. First off, I'm not sure why but at master level setting the font and background colors for summary lines does not work except for summary line that are in a subproject. However, you can use the Marked field for set up formatting for all summary lines at master level, just add that field and set it to "yes" for all summary lines.
The next thing you need to do to get the graphical indicators to show as intended is to check the boxes to show indicators at summary level.
Hope this helps.
John
- John-projectDec 24, 2021Silver Contributor
I don't quite understand your statement, "I do not want graphical indicators in my subproject line". What exactly do you mean by "subproject line"? Are you referring to the summary line insertion points in the master like I show in my screen shot? So where exactly do you, and do you not, want the graphical indicators to appear?
Where you apply graphical indicators is up to the user. It just becomes a little more challenging when working with a master file with inserted subprojects.
Before you get to comfortable with master/subproject structures in Project let me inform you of some rules. Never rename, move, overwrite, or save off to another location any of the files in the structure. Dynamic masters (master with inserted subprojects) in Project are prone to corruption. Violating the above will practically guarantee the structure will get corrupted. Also, it is best to keep all files in a single folder on a local drive and not operate over a network.
John
- ajaffkeDec 23, 2021Copper Contributor