Forum Discussion

KrysM380's avatar
KrysM380
Copper Contributor
Jun 23, 2022

Conditional Formatting for MS Project 365

I know MSP does not have conditional formatting available but i have seen some VBA code that others have done but doesn't fit my needs and im not a VBA programmer.

 

I have an enterprise field (schedule not on PO located in Sharepoint, not my choice) which has a lookup with 3 options.

  • Tapped 
  • In Progress 
  • Completed 

I need to be able to highlight the entire row depending on the value in the lookup.

 

for example: 

  • Tapped - lightest orange
  • In Progress - lightest blue
  • Completed - lightest green

does anyone have some code that could help.  the name of the custom field is Tapping Status1

 

Please help we are doing a large deployment and the cutover schedule is really large and being able to quickly identify the status of each task quickly is imperative 

 

5 Replies

  • John-project's avatar
    John-project
    Silver Contributor
    KrysM380,
    Yeah, I can probably help. Where did you see the VBA code?

    It will be easier if I can actually see your Project file. Are you able to share it with me? If so, my contact address is below. I will ask some questions.
    John
    jmacprojataticlouddotdotcom
    (remove obvious redundancies)
    • KrysM380's avatar
      KrysM380
      Copper Contributor

      John-project 

       

      John sorry cant share the file it is classified and 7800 lines 

       

       

       

      This is a snapshot as you can see the the Column Tapping Status 1 has a lookup field comprising 3 entries "In Progress" Tapping Sent" and "Completed".  when I select tapping sent i want the whole row to be shaded in orange and if i select complete the row changes to green and the same for In Progress 

       

      I dont remember where i saw the vba code i was searching the internet for hours.

       

      are you able to assist.

       

      thanks 

       

      Krys

      • John-project's avatar
        John-project
        Silver Contributor

        Krys,
        I asked about where you saw the VBA code since it's quite likely I wrote it for another user. At any rate I can still help you. However, there is no "Tapping Status" field so I'm guessing it's an extra field (e.g. Text1) that you renamed but in order to write a macro, I need to know which field it is.

        When you say "shaded" in a particular color I assume you mean the task row's cell background color.

        I may have more questions, but answers to the above should get it started.

        By the way, are you available over the weekend? That's when I do this kind of stuff. Even if you can't directly share the file, communicating via e-mail is generally easier and more convenient.

         

        One other curious observation, if your file is classified, is the client/customer going to allow a macro you get from someone on the internet to be run on the file?
        John