Concept of group and subgroup

hello All, what is the best way to introduce the concept of group and subgroup for the resources in Project? For example, we have 2 subgroups: subgroup 1 for Sw engineers (5 persons), named SWE in...
  • Dale_HowardMVP's avatar
    Dale_HowardMVP
    Aug 30, 2021
    demetrio61 --

    If you are not using Project Online or Microsoft Project Server, you would need to create a shared resource pool file. In that file, you would need to add the custom Outline Code field, along with all of your resources. Hope this helps.