Forum Discussion

Alina_Andreica's avatar
Alina_Andreica
Copper Contributor
Aug 22, 2023

Computing tasks Finish date in Project

Hello,   I've unexpectedly run into the following situation: for a project, I've set the work schedule for 4hours / day and entered a task with the duration of 40hours, which I've computed as 10 wo...
  • John-project's avatar
    John-project
    Aug 22, 2023
    Alina_Andreica,
    You need to have a custom 4h workday calendar. If it only applies to those two tasks, then use the Task Calendar field to set the 4h workday calendar for those tasks and leave the Standard calendar as your Project calendar.

    Also, if the 4h workday is limited to certain tasks, do NOT change the definition of a "day" to 4 hours, leave it at the default 8h or whatever a standard day is for the rest of the tasks. Project only allows one definition of a "day" so if you have a mixed bag, I suggest you either stick with entering duration values in hours (that works for everything), or only used days in the duration field for non-4h day tasks. The 4h workday task duration will still need to entered in hours.

    Understand that Project calculates all time values to the nearest minute regardless of the setting you use for duration.

    John