Forum Discussion
BrianNeil3377
Feb 24, 2022Brass Contributor
Completed projects in P4W
What do PM's typically do when they have completed all tasks in a project and close it out? Is there a way to archive the project? Its a completed project so I dont want it on my list of active proj...
BrianNeil3377
Mar 28, 2022Brass Contributor
If I were to "Export to Excel" a completed Project for the Web project, can that Excel file be reimported into Project for the Web for future use? Or can I convert the completed project into a .mpps file which can be opened by my installed Project client and then imported in Project for the Web.
Mar 29, 2022
Brian --
No, you would not be able to import the Excel work information back into Project for the Web. You would be able to import the data into the Microsoft Project, but it would require quite a bit of cleanup to the data to make it compatible with Microsoft Project. Hope this helps.
No, you would not be able to import the Excel work information back into Project for the Web. You would be able to import the data into the Microsoft Project, but it would require quite a bit of cleanup to the data to make it compatible with Microsoft Project. Hope this helps.