There are two ways to reschedule delayed work from the status date:
Manual:
Select the task > Menu > Tasks > Move > Incomplete Parts to Status Date
or Select the task > Menu > Project > Status > Update Project > Reschedule uncompleted work to start after: > For: Selected tasks > OK
Automatic: Menu > File > Options > Advanced > Calculation options for this project > Select: Move start of remaining parts before status date forward to status date
Note: In this automatic case, for tasks you want to reschedule that had progress before this new option was changed, you will need to re-enter the % complete or Actual Duration, or even delete the value and re-enter it if the above doesn't work.
For any new progress entered for any task that is delayed, it will be automatically rescheduled based on the status date.
I hope this helps.