Forum Discussion

stevenj's avatar
stevenj
Copper Contributor
Nov 30, 2025

%Complete didnt change the Finish Duration

I have an issue on my Microsoft Project work, when I update the %Complete on a single task (tracking mode) the Finish duration didnt change (the task type is Fixed Units).   For example:   My tas...

Resources