%Complete didnt change the Finish Duration
I have an issue on my Microsoft Project work, when I update the %Complete on a single task (tracking mode) the Finish duration didnt change (the task type is Fixed Units). For example: My tas...
TrevorATperfectproject
Dec 01, 2025Brass Contributor
The status date is the vertical red line.
Line 1. If the task has been continuously in progress since 20/11/2025, all of the days from 20/11/2025 up to the status date are actual duration (7 days), and the remaining incomplete duration is 5 days and they are all in the future. relative to the status date.
Line 2. If the task actually started on 20/11/2025, and % complete is 10%, the actual duration is 1.2 days.
Line 3. All of the remaining incomplete part must be moved to the status date.
Any help?