Forum Discussion
Knowledgeseeker
Aug 23, 2023Brass Contributor
Compare current value with the new inputted value
Hi Community, As I know when editing a finishdate, the new date will replace the previous one, is there any way to compare these values before saving the changes: lets say the current FinishDate i...
- Aug 27, 2023Knowledgeseeker,
Pardon me for bumping in to this thread. It sounds like you are trying to do a couple of things.
1. If a task finish date is 10 (or more) days later than its previous date, you want a flag raised
2. You want a metric to show how many times a task finish date changed since "day 1" of the plan.
I doubt you'll find any kind of update table where you can extract that type of information but you could have an event based macro that gives you both pieces of data as stated above. That would be a lot easier than jockeying with the baseline data.
Just a thought.
John
Aug 23, 2023
Knowledgeseeker --
You need to save a Baseline in your project before you enter progress. You can then compare the difference between the Baseline Finish date and the Finish date using the task Variance table (click View > Tables > Variance to apply it). Hope this helps.
You need to save a Baseline in your project before you enter progress. You can then compare the difference between the Baseline Finish date and the Finish date using the task Variance table (click View > Tables > Variance to apply it). Hope this helps.
- KnowledgeseekerAug 24, 2023Brass ContributorHi Dale Howard
As I know the maximum number of baselines is 10, in case I wanted to add more I will have to rewrite over others, in other words, I will loose the history of baselines.
Please correct me if I am wrong.
Thank you in advance.- Aug 24, 2023Knowledgeseeker --
Actually, the maximum number of baselines is 11 in Microsoft Project. They are Baseline (aka Baseline 0), along with Baseline 1-10. The baseline should be the original starting values in your project, to which you can compare your current schedule to see project variance. Why do you need so many baselines, out of curiosity? Let us know and we will try to help you.- KnowledgeseekerAug 24, 2023Brass ContributorI will clarify more the scenario I am working on.
For a given project X, each time a new baseline is created I need to compare it with the previous one to make sure if the new variance is higher or the opposite.
I thought of going through the table ProjectBaseline but I did not find such historical changes to do the comparaison.
I hope it's clear and I can answer other questions if there are any.
Thank you in advance.