Forum Discussion
NaomiBrill
Nov 06, 2023Brass Contributor
Colleagues not able to see projects in Project Center
There are 6 members of my team who have all been given admin permission to our Project plan (so everyone can add their annual leave to the Resource Center), however some members cannot see some proje...
- Nov 07, 2023
I've just discovered that the projects that my colleagues can't see are subprojects - not sure why or how they are set up differently to the others, but I've worked out that my colleagues just need to check the 'subprojects' box to see them!
Nov 06, 2023
Naomi --
I think you may be doing something wrong. How did you give these users admin permissions? The correct way to do this is to add them to the default Administrators security group in PWA. When you do that, they will automatically be given permissions to view all published projects in the Project Center page in PWA. There is no need to "share" the projects with anyone. Hope this helps.
I think you may be doing something wrong. How did you give these users admin permissions? The correct way to do this is to add them to the default Administrators security group in PWA. When you do that, they will automatically be given permissions to view all published projects in the Project Center page in PWA. There is no need to "share" the projects with anyone. Hope this helps.
NaomiBrill
Nov 07, 2023Brass Contributor
Hi Dale,
I can confirm that my colleages can see the projects in the PWA and open them in the Project Center, but they can't see/access them directly from the Project Center and therefore can't edit them in the desktop app. Any ideas?
Thanks so much,
Naomi
I can confirm that my colleages can see the projects in the PWA and open them in the Project Center, but they can't see/access them directly from the Project Center and therefore can't edit them in the desktop app. Any ideas?
Thanks so much,
Naomi