Collapsing a master / Sub plan with links between projects into a single file
I have a simple master plan with 3 inserted files. There are dependencies between the files, indicated by a Dep in / out field and a unique reference. I have a macro which can make and break electr...
John-project
Nov 10, 2022Silver Contributor
Miles,
As I noted in the Stack Overflow "forum" I have a macro that will create a "flat" file from a linked master while preserving all the inter-project links. If you want more information contact me at the address listed below.
As far as using your existing macros to do the same thing, I have no idea so that is indeed something for you to ponder.
John
jmacprojataticlouddotdotcom
(remove obvious redundancies)
As I noted in the Stack Overflow "forum" I have a macro that will create a "flat" file from a linked master while preserving all the inter-project links. If you want more information contact me at the address listed below.
As far as using your existing macros to do the same thing, I have no idea so that is indeed something for you to ponder.
John
jmacprojataticlouddotdotcom
(remove obvious redundancies)
- MilesGoodchildNov 10, 2022Copper Contributor
Email sent, hopefully I passed the "remove the redundancies" test; the atat foxed me briefly 🙂 🙂
- John-projectNov 10, 2022Silver ContributorMiles,
No message yet (1 hour after your posting). Hopefully you also got the dotdot redundancy. Over the years I've only had a couple of people not figure it out. I use the encoding of course to prevent spam bots and thus far it's worked great.
John- Miles_GoodchildNov 10, 2022Brass Contributor
John-project **bleep**, looks like I'll have to try again 🙂