Forum Discussion

AlexTramac's avatar
AlexTramac
Copper Contributor
May 24, 2023
Solved

Close task at 100%

HELLO, I have been working in MS Project for a short time. I would like to know how to automate the advancement of tasks that follow another task that ended earlier than planned.  I put 100% on a ta...
  • John-project's avatar
    John-project
    May 24, 2023
    AlexTramac,
    Simply setting a task at 100% via the Percent Complete field will not change the schedule dates. Project will assume the task started and finished on the schedule dates. As Dale noted, if a task finishes early, you need to enter the actual finish date into the Actual Finish field. Project will then set the task at 100% AND will automatically update the task scheduled finish date to agree with the actual finish date. If the task has successors that are not constrained (e.g. start-no-earlier-than), the start date for those successor tasks will move up.

    John

Resources