Forum Discussion
AurelioDM
Oct 26, 2023Copper Contributor
Checklist grayed out in Project for the web
Hi all We are experiencing an issue with our checklist functionality. All of our users are equipped with Business Premium licenses, while our administrators have Plan 3 licenses for Projects. The...
- Oct 26, 2023AurelioDM --
I believe each of your team members will need a Project Plan 1 license in order to update Checklist information in their projects. Hope this helps.
AurelioDM
Nov 02, 2023Copper Contributor
Thank you for the reply. Just strange that this requirement isn't mentioned in the help page.
RodFromm
Nov 02, 2023Steel Contributor
AurelioDM It's not easy to find, but it's mentioned in this doc Microsoft Project for the web service description - Service Descriptions | Microsoft Learn
* Microsoft 365 and Office 365 E3 and E5 can update a limited set of fields (Mark as complete, Progress) on tasks assigned to them.