Changing working and non working days in MS project

I changed the non working day to Friday but the graph does not skip Friday. What can i do?

1 Reply

  • John-project's avatar
    John-project
    Silver Contributor

    Kiran19961001

    From your screen shot it looks like Friday IS the non-working day. However, if you are expecting the Gantt bar to not show on Friday, then you need to set the timescale display to show the non-working time in front of the task bars.

    John