Changing Task Information for Multiple Tasks - Microsoft Project Online Desktop
The version I currently use is Microsoft® Project® Online Desktop Client MSO (Version 2310 Build 16.0.16924.20054) 64-bit and I have been able to notice that the functionality to change the value of ...
- Nov 02, 2023rbuzeta,
It sounds like you got some bad information from whomever you talked to at Microsoft. The problem you report was recently reported and is apparently do to an artifact of a recent update. Please see this post:
https://techcommunity.microsoft.com/t5/project/bulk-edit-not-working/m-p/3935750
John
Mohammad2352030
Dec 27, 2023Copper Contributor
Ignacio_Martin
Dec 27, 2023Iron Contributor
Ignacio_Martín replied to Kdekruif
Dec 18 2023 12:11 PM
Kdekruif
Good news!
I just checked that the latest update to Project Professional, version: Microsoft® Project® Online Desktop Client MSO (Version 2312 Build 16.0.17126.20078) 64-bit, fixes and restores the functionality of replacing selected task values, through Task Information dialog box (Task Information).
In addition to the automatic update, I remind you that you can try the update in bar menu > File > Account > Update Options > Update Now
Ignacio
Dec 18 2023 12:11 PM
Kdekruif
Good news!
I just checked that the latest update to Project Professional, version: Microsoft® Project® Online Desktop Client MSO (Version 2312 Build 16.0.17126.20078) 64-bit, fixes and restores the functionality of replacing selected task values, through Task Information dialog box (Task Information).
In addition to the automatic update, I remind you that you can try the update in bar menu > File > Account > Update Options > Update Now
Ignacio
- Christopher SneedApr 15, 2024Copper ContributorI updated to this build: Microsoft® Project® Online Desktop Client MSO (Version 2403 Build 16.0.17425.20176) 64-bit. Bulk edit using the Task Information dialog box when multiple tasks are selected is not working for me. I was able to add the column "Type" to the view. Then I used the handle to copy "Fixed Duration" to the tasks below. A decent work around, but too bad I can't change multiple tasks using that dialog box. I used to be able to do this in previous desktop versions.
- John-projectApr 15, 2024Silver ContributorChristopher Sneed,
Sorry but I don't know what to say. It works for me and I have the same update version. You might try a repair of Project but I'm not sure how that works with a subscription version of Project.
John