Forum Discussion
rbuzeta
Nov 01, 2023Tin Contributor
Changing Task Information for Multiple Tasks - Microsoft Project Online Desktop
The version I currently use is Microsoft® Project® Online Desktop Client MSO (Version 2310 Build 16.0.16924.20054) 64-bit and I have been able to notice that the functionality to change the value of ...
- Nov 01, 2023rbuzeta,
It sounds like you got some bad information from whomever you talked to at Microsoft. The problem you report was recently reported and is apparently do to an artifact of a recent update. Please see this post:
https://techcommunity.microsoft.com/t5/project/bulk-edit-not-working/m-p/3935750
John
rbuzeta
Nov 01, 2023Tin Contributor
Thx John
John-project
Nov 01, 2023Silver Contributor
rbuzeta,
You're welcome and thanks for the feedback.
By the way, if Microsoft still wants to charge you for the ticket, I would protest.
John
You're welcome and thanks for the feedback.
By the way, if Microsoft still wants to charge you for the ticket, I would protest.
John
- rbuzetaNov 21, 2023Tin ContributorAccording to new information received from Microsoft support staff, it is estimated that the solution to this BUG could be deployed on December 12, 2023
- Mohammad2352030Dec 27, 2023Copper Contributor
- Ignacio_MartinDec 27, 2023Steel ContributorIgnacio_Martín replied to Kdekruif
Dec 18 2023 12:11 PM
Kdekruif
Good news!
I just checked that the latest update to Project Professional, version: Microsoft® Project® Online Desktop Client MSO (Version 2312 Build 16.0.17126.20078) 64-bit, fixes and restores the functionality of replacing selected task values, through Task Information dialog box (Task Information).
In addition to the automatic update, I remind you that you can try the update in bar menu > File > Account > Update Options > Update Now
Ignacio