Changing amount to MIllion
Is there any way to cenvert an amount to Million in the cost field? I am unable to do the same. I am working on MS Project ver 2016.
- Jan 10, 2023Prosenjit0802,
You can also do it in Project but you'll have to use a Text field (e.g. Text1), but it can't be shown that way in any Cost field.
John
Ignacio_Martin
Jan 15, 2023Steel Contributor
Hi Jan.
You can try to put Million in the options (File/ Options/ Display/ Currency Symbol = Million), but you would have to enter or paste the values.